Keltie Water

Drummond Estate, Callandar, Scotland 

At over 1,800 sq km and as one of the UK’s largest National Nature Reserves, the Trossachs National Park attracts over 4 million visitors each year. There are currently 38 operational, run-of-river hydro schemes within the Park, of which Keltie Water is one of the larger, privately developed examples.

The 1MW Keltie Water hydro scheme, which is Gilkes second machine for the Drummond Estate, was granted planning permission in 2014 and construction started the following year. Gilkes worked closely with consultants, Allt Energy, and civil engineers, Campbell of Doune Ltd, throughout the early stages of the project - ultimately selecting a 25” twin-jet Turgo as the most suitable machine for the scheme.

The faster running nature of the Turgo, along with its broad efficiency characteristics and low profile, all fitted well with the scheme’s hydrology and planning constraints. The scheme has two intakes, the main intake being located on a dam formerly owned by Scottish Water, from which the scheme only abstracts when the dam spills. The second intake is a conventional run of river intake which highlights the importance of the Turgo’s flat efficiency curve.

The Turgo is particularly suited to this site with its ability to operate across a flow range of ~1.63m3/s to 0.15m3/s with a nett head of 78m, and while running at 600rpm. In contrast to a slower running vertical machine (which would require a considerably taller building) the simplicity, high speed and lower cost of the Turgo also allowed a lower profile stone built Powerhouse to be sited. Sensitively, resulting in a scheme that is nicely absorbed by the surrounding landscape.

Although large by UK standards, the Turgo turbine at Keltie Water shares its advantages with considerably higher output machines abroad. Gilkes has supplied over 1000 Turgos to over 40 countries, with some examples generating in in excess of 7.5MW from a single machine.

Gilkes provide a comprehensive service and maintenance package not only to the Keltie scheme but also schemes across the Trossachs from our recently opened Scottish service centre in Callander, dedicated to serving the Trossachs and surrounding areas.

Gilkes continues to make substantial investments in advancing the Turgo design today - more than 100 years after the company patented the design in 1919.

 

SCOPE OF SUPPLY 

  • 25" Twin Jet Impulse Turbine
  • Main inlet valve
  • Synchronous generator
  • Lube oil system
  • Control & switchgear panel
  • Hydraulic control module
  • Head level sensor
  • Control & power cabling
  • Building services
  • Transformer
  • Installation & commissioning
  • Servicing for duration of warranty
DOWNLOAD FULL CASE STUDY download

Key Stats

  • Commissioned February 2016
  • Power 1000 kW
  • Net Head 78 M
  • Flow 1626 l/s
  • Turbine HCTI Twin Jet Turgo